This page has been archived.
Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
The Mid-Shore Patrol Vessels (MSPV) project will acquire 9 Mid-Shore Patrol Vessels for the Canadian Coast Guard (CCG) Fleet - five of the nine MSPV will be used primarily to support the Conservation and Protection Program in the Maritimes, Quebec and Pacific Regions. The other four vessels will be used in a joint program with the Royal Canadian Mounted Police (RCMP) to enhance maritime security along the Great Lakes – St. Lawrence Seaway system. This project serves two purposes:
Fleet Renewal - the acquisition of conservation and Protection patrol vessels represents the first step in modernization of the CCG fleet and will ensure the integrity of the fishery monitoring program and will provide the capacity for DFO to support the strategic role in fisheries enforcement; and
Maritime Security - the acquisition of MSPV for Maritime Security will allow CCG, in conjunction with the RCMP, to respond to the Government's commitment to enhance the security of the nation's coasts and waterways.
The MSPV Project is currently in the Construction phase.
Lead Department or Agency | Canadian Coast Guard, Department of Fisheries and Oceans |
---|---|
Contracting Authority | Public Works and Government Services Canada |
Participating Departments | Industry Canada; RCMP; Treasury Board Secretariat; Privy Council Office; Aboriginal Affairs and Northern Development Canada; Atlantic Canada Opportunities Agency; Western Economic Diversification Canada; Canadian Economic Development; Finance Canada; Public Safety Canada; Department of National Defence. |
Prime Contractor |
Irving Shipbuilding Inc. P.O. Box 9110, 3099 Barrington Street Halifax, Nova Scotia B3K 5M7 Operating as: Halifax Shipyard |
---|---|
Major Sub-contractor(s) | International Contract Engineering, Damen, Lloyd's Register, MTU. |
The MSPV project supports the Vessel Procurement and Fleet Renewal Objectives of the Canadian Coast Guard.
Project milestones have been developed and served as outcomes for the MSPV project. Coast Guard's Vessel Procurement Sector is currently developing a Performance Measurement Framework for 2011-12, in line with changes being undertaken to the DFO Program Activity Architecture and Management, Resources and Results Structure.
All 2010-11 objectives for the MSPV project were achieved. The procurement of nine MSPVs by 2014 is on track.
In August 2009, a contract was awarded to Irving Shipbuilding Inc. for the procurement of 9 MSPV. Construction of the first vessel began in September 2010.
Canadian industry will benefit from this project. The Request for Proposal requires overall Industrial Benefits equal to 100% of contract value. Regional allocation of industrial benefits is monitored by Industry Canada.
Major Milestone | Date |
---|---|
Preliminary Project Approval | August 2005 |
Effective Project Approval | June 2006 |
1st Request for Proposal (RFP) (cancelled) | July 2007 |
Amended Effective Project Approval – to include 4 additional vessels identified in Budget 2007 | December 2007 |
2nd Request for Proposal issued (cancelled) | August 2008 |
3rd Request for Proposal issued | March 2009 |
Contract Awarded | August 2009 |
First Vessel Delivery | Winter 2012 |
Delivery of final MSPV | Winter 2014 |
The Offshore Fisheries Science Vessels (OFSV) project will acquire three OFSV for the Canadian Coast Guard (CCG) Fleet. The OFSV will replace four aging Coast Guard ships on the east and west coasts of Canada that provide a platform from which critical scientific research and ecosystem-based management can be performed.
The OFSV Project is currently in the design phase.
Lead Department or Agency | Canadian Coast Guard, Department of Fisheries and Oceans |
---|---|
Contracting Authority | Public Works and Government Services Canada |
Participating Departments or Agencies | Industry Canada; Treasury Board Secretariat; Privy Council Office; Aboriginal Affairs and Northern Development Canada; Atlantic Canada Opportunities Agency; Western Economic Diversification Canada; Canadian Economic Development; Finance Canada. |
Prime Contractor | To be determined |
---|---|
Major Sub-contractor(s) | Design Contractor: Robert Allan Ltd., Alion Science and Technology (Canada) Corporation and Alion Science and Technology Corporation in joint venture. |
The OFSV project supports the Vessel Procurement and Fleet Renewal Objectives of the Canadian Coast Guard. Project outcomes contribute to the Fleet Operational Readiness Program Activity in DFO's Program Activity Architecture.
The 2010-11 Report on Plans and Priorities commitment was met. During 2010-11, the concept design phase was finalized and the project progressed into the Preliminary Design phase. In June 2010, the Government of Canada announced that the three OFSV will be built under the National Shipbuilding Procurement Strategy (NSPS). Currently, the project is on schedule to meet the timelines identified for NSPS with the design contract completion scheduled for Fall 2011 and Construction Contract Award scheduled for Spring 2012. Two OFSV are planned to be delivered by 2014 and one in 2015.
Project milestones have been developed and served as outcomes for the OFSV project. Coast Guard's Vessel Procurement Sector is currently developing a Performance Measurement Framework for 2011-12, in line with changes being undertaken to the DFO Program Activity Architecture and Management, Resources and Results Structure.
Canadian industry will benefit from this project. Regional distribution will be determined at contract award.
Major Milestone | Date |
---|---|
Preliminary Project Approval | October 2005 |
Amended Preliminary Project Approval | November 2006 |
2nd Amended Effective Project Approval – to include 4 additional vessels identified in Budget 2007 | June 2009 |
Issue Request for Proposal for Design | Spring 2010 |
Government of Canada announced that the three Offshore Fisheries Science Vessels will be built under the National Shipbuilding Procurement Strategy | June 2010 |
3rd Amended Preliminary Project Approval — to award contract | September 2010 |
Issue Design Contract | October 2010 |
Design Contract Completion | Fall 2011 |
Effective Project Approval — Target Date | Winter 2012 |
Construction Contract Award | Spring 2012 |
First two Vessels to be delivered | 2014 |
Delivery of final OFSV | 2015 |
The Offshore Oceanographic Science Vessel (OOSV) project will acquire a replacement vessel for the Canadian Coast Guard's largest science vessel - CCGS Hudson. This vessel was built in 1963 and its replacement is critical to fulfilment of the Department's science mandate as well as mandates of other government departments and agencies. The vessel currently operates on the east coast of Canada.
The OOSV Project is currently in the design phase.
Lead Department or Agency | Canadian Coast Guard, Department of Fisheries and Oceans |
---|---|
Contracting Authority | Public Works and Government Services Canada |
Participating Departments or Agencies | Industry Canada; Environment Canada; Natural Resources Canada; Treasury Board Secretariat; Privy Council Office; Aboriginal Affairs and Northern Development Canada; Atlantic Canada Opportunities Agency; Western Economic Diversification Canada; Canadian Economic Development; Finance Canada. |
Prime Contractor | To be determined |
---|---|
Major Sub-contractor(s) | Design Contractor: STX Canada Marine Inc. |
The OOSV project supports the Vessel Procurement and Fleet Renewal objectives of the Canadian Coast Guard.
Project milestones have been developed and served as outcomes for the OOSV project. Coast Guard's Vessel Procurement Sector is currently developing a Performance Measurement Framework for 2011-12, in line with changes being undertaken to the DFO Program Activity Architecture and Management, Resources and Results Structure.
The 2010-11 Report on Plans and Priorities commitment was met. In June 2010, the Government of Canada announced that the Offshore Oceanographic Science Vessel would be built under the National Shipbuilding Procurement Strategy (NSPS). Currently, the project is on schedule to meet the timelines identified for NSPS with the design contract completion scheduled for Fall 2011 and construction contract award scheduled for Spring 2012. The vessel is scheduled to be delivered in late 2014 rather than 2013.
Canadian industry will benefit from this project. Regional distribution will be determined at contract award.
Major Milestone | Date |
---|---|
Preliminary Project Approval | July 2008 |
Government of Canada announced that the three Offshore Oceanographic Science Vessel will be built under the National Shipbuilding Procurement Strategy | June 2010 |
Contract Award for Design | Fall 2010 |
Design Completion | Fall 2011 |
Effective Project Approval – Target Date | Winter 2012 |
Construction Contract to be Awarded | Spring 2012 |
Delivery of OOSV | Late 2014 |
The new Polar Icebreaker is expected to be delivered in time for the decommissioning of the CCGS Louis S. St-Laurent. This new polar icebreaker will help strengthen Canada's Arctic sovereignty and will be able to operate in the Arctic in more difficult weather conditions and for a longer period of time - 3 seasons instead of the current 2 seasons.
The Polar Icebreaker Project is currently in the definition phase.
Lead Department or Agency | Canadian Coast Guard, Department of Fisheries and Oceans |
---|---|
Contracting Authority | Public Works and Government Services Canada |
Participating Departments or Agencies | Industry Canada; Treasury Board Secretariat; Privy Council Office; Aboriginal Affairs and Northern Development Canada; Atlantic Canada Opportunities Agency; Western Economic Diversification Canada; Canadian Economic Development; Finance Canada; Environment Canada; National Defence. |
Prime Contractor | To be determined |
---|---|
Major Sub-contractor(s) | n/a at this time |
The Polar Icebreaker project supports the Vessel Procurement and Fleet Renewal objectives of the Canadian Coast Guard, and supports the Government's Northern Strategy.
Project outcomes contribute to the Fleet Operational Readiness Program Activity in DFO's Program Activity Architecture.
The 2010-11 Report on Plans and Priorities commitment was met. The Baseline Requirements were developed and finalized in 2010-11 and are now being used to instruct and guide the Conceptual Design Package. The Polar Icebreaker is scheduled for delivery in 2017.
Canadian industry will benefit from this project. Regional distribution will be determined at contract award.
Major Milestone | Date |
---|---|
Preliminary Project Approval | June 2009 |
Design Contract Awards — Target Date | 2011 |
Effective Project Approval — Target Date | 2013 |
Contract Award (Construction) | 2013 |
Delivery of Polar Icebreaker | 2017 |
The Government of Canada is procuring an Air Cushion Vehicle (ACV or hovercraft) to replace CCGS Penac at the Canadian Coast Guard Sea Island Hovercraft Base in Richmond, British Columbia. It will provide ongoing search and rescue coverage in the area, allowing CCG to continue to fulfill its mandate and maintain current levels of service.
The Air Cushion Vehicle (ACV) is currently in the construction phase.
Lead Department or Agency | Canadian Coast Guard, Department of Fisheries and Oceans |
---|---|
Contracting Authority | Public Works and Government Services Canada |
Participating Departments or Agencies | Treasury Board Secretariat |
Prime Contractor | Griffon Hoverwork Ltd. Merlin Quay, Hazel Road, Woolston, Southampton SO19-7GB United Kingdom. |
---|---|
Major Sub-contractor(s) | Aluminium Marine Consultant's Limited of Cowes, Isle of Wight (Hull Manufacture /Craft fit out). |
The ACV project supports the Vessel Procurement and Fleet Renewal objectives of the Canadian Coast Guard. Project outcomes contribute to the CCG Pacific Fleet Search and Rescue operational readiness.
Contractor's proposal and contract negotiations were not completed until March 2011. Contract was awarded on March 15, 2011.
Not applicable, as craft is being built in England.
Major Milestones | Date |
---|---|
Project announced in Federal Budget 2010 | March 2010 |
Effective Project Approval | May 2010 |
ACAN put on MERX September 2009, closed September 28, 2010 No challenges to the ACAN were received from Canadian Industry | September 2010 |
Meeting with the proposed Contractor Griffon Hoverwork Ltd. on the Isle of Wight England mid November 2010. Discussed pro-forma contract, TSOR, Delegated Statutory Inspection Regime and Lloyd's Register | November 2010 |
TSOR Clarifications issues received from GHW Ltd. and CCG response early December 2010 | December 2010 |
GHW Ltd Submits a priced proposal January 07, 2011 | January 2011 |
Following the Crown's review of the Contractor's proposal and successful contract negotiations the contract was awarded to GHW Ltd. on March 15,2011 Contract Award (Construction) | March 15, 2011 |
Delivery of the Air Cushion Vehicle | Fall 2013 |