Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Internal Audits and Evaluations

Internal Audits (current reporting period)

The following activities were included in the CNSC risk-based Audit Plan for the period 2009-10 to 2011-12. This plan was updated in 2010 and 2011.

The latest updated plan was submitted to the CNSC’s Audit Committee in May 2011 for review and recommendation for approval by the CNSC’s President. It is based on the current capacity of the CNSC’s audit function, risk assessments of proposed audit projects, and management responses and action plans for prior audits for follow-up. The revised plan outlines the projects planned for the upcoming three years 2011-12 to 2013-14. Projects undertaken depend on factors such as resources available to the audit function, the scope and complexity, of projects, and the CNSC’s emerging issues and priorities.

The Commission has an Audit Committee with members who are external to the government and internal to the Commission. The Committee is chaired by an external member.

Additional information on the CNSC Internal Audits is available on the CNSC Web site.

Name of Internal Audit Internal Audit Type Status Completion Date
Audit of Compliance Enforcement Compliance and management audit 2010-11 Completed
Audit of Revenue Management Financial Audit 2010-11 Completed
Preliminary Survey of Risk Management Survey 2010-11 Completed
Audit of Inspector Qualification and Training Compliance and management audit 2010-11 Postponed
Audit of Delegated Licensing Authority Compliance and management audit 2010-11 Postponed
Audit of Regulatory Document Development Compliance and management 2010-11 Completed
Audit of Corporate Governance Compliance and management audit 2010-11 Postponed
Monitoring of action plans from past audits Monitoring 2010-11 Ongoing
Follow-up on past audits, including Procurement Audit Follow-up 2010-11 Ongoing
The audit conducted is not included in the risk-based audit plan for the period 2010-2011
Audit of Travel and Hospitality Compliance and management audit 2010-11 Completed

Evaluations

In recent years, the oversight function at CNSC has been primarily the responsibility of internal audit. The Government of Canada Policy on Evaluation (the Policy) approved April 2009 revitalized evaluation to provide another element to the oversight function by demonstrating to Canadian’s value-for-money of government spending.

The CNSC began strengthening the evaluation function in Fiscal Year 2009-2010 to ensure alignment with the Policy. In 2010-2011 DG of Strategic Planning Directorate was designated as Head of Evaluation, and the Evaluation division was created (Regulatory Research and Evaluation Division). The majority of effort was focused on drafting the evaluation policy as well as the Evaluation Committee Terms of Reference. Further, the evaluation universe was identified and the Evaluation Plan was developed and approved April 2011.

2011-2012 will continue to strengthen the function and increase evaluation capacity through staffing of a Senior Evaluation Officer and an Evaluation Officer positions reporting to the Director of Regulatory Research and Evaluation. There is a commitment to conduct 4 evaluation projects this fiscal, as well as further develop and refine the Evaluation Policy Suite.

Evaluation Reports Planned for FY 2011-2012

Name of Evaluation Program Activity Status Completion Date
Canadian Safeguards Support Program Evaluation Regulatory Framework In-progress September 15, 2011
Labour Management Consultation Committee Evaluation Internal Services In-Progress December 15, 2011
Nuclear Standards Program of the Canadian Standards Association Evaluation Regulatory Framework In-Progress December 15, 2011
Performance Measurement Evaluation Internal Serviced Planning Phase February 2011