Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Project | Original Estimated Total Cost 1 |
Revised Estimated Total Cost 2 |
Actual Cost Total 3 |
2010-11 | ||||
---|---|---|---|---|---|---|---|---|
Main Estimates |
Planned Spending4 |
Total Authorities5 |
Actual | Expected date of close-out6 |
||||
Internal Services | ||||||||
Close-Out | ||||||||
Housing infrastructure, B.C. and Yukon | 10,000 | 10,000 | 9,623 | 9,574 | 9,574 | 9,582 | 9,205 | 2010–11 |
St. Stephen, N.B. | 21,508 | 21,508 | 22,811 | 100 | 100 | 100 | 97 | 2010–11 |
Implementation and Development | ||||||||
Non-housing Infrastructure, B.C. and Ontario | 70,000 | 70,000 | 11,920 | 23,798 | 11,132 | 32,795 | 10,792 | 2011–12 |
Douglas, B.C. | 45,000 | 45,000 | 47,692 | 312 | 312 | 312 | 241 | 2011–12 |
Andover, N.B. | 6,445 | 6,445 | 8,094 | 327 | 192 | 327 | 192 | 2011–12 |
Rigaud, Quebec | 54,000 | 57,574 | 9,742 | 25,877 | 6,349 | 25,877 | 5,352 | 2012 –13 |
Saint-Bernard-de-Lacolle,Quebec (commercial expansion) | 10,000 | 10,000 | 429 | 476 | 443 | 476 | 306 | 2013–14 |
Harmonized Risk Scoring-Advance Trade Data | 5,575 | 5,575 | 2,102 | 1,129 | 1,129 | 1,129 | 406 | 2011–12 |
Air Cargo | 1,184 | 1,184 | 153 | 690 | 153 | 2011–12 | ||
eManifest | 19,800 | 19,800 | 11,597 | 2,025 | 3,603 | 3,603 | 3,264 | 2013–14 |
Initial Planning and Identification | ||||||||
Beaver Creek, Yukon | 6,600 | 6,600 | 507 | 253 | 253 | 253 | 253 | 2013–14 |
Aldergrove, B.C. | 15,000 | 12,000 | 183 | 86 | 86 | 86 | 29 | 2013–14 |
Total Internal Services | 265,112 | 265,686 | 124,853 | 63,957 | 33,173 | 75,230 | 30,290 | |
Risk Assessment | ||||||||
Implementation and Development | ||||||||
eManifest | 316,801 | 316,801 | 185,549 | 32,401 | 57,654 | 57,654 | 52,226 | 2013–14 |
Harmonized Risk Scoring-Advance Trade Data | 33,289 | 33,289 | 15,879 | 6,740 | 6,740 | 6,740 | 4,938 | 2011–12 |
Air cargo | 5,138 | 5,138 | 2,039 | 2,335 | 2,039 | 2011–12 | ||
Total Risk Assessment | 355,228 | 355,228 | 203,467 | 39,141 | 64,394 | 66,729 | 59,203 | |
Conventional Border | ||||||||
Implementation and Development | ||||||||
eManifest | 59,400 | 59,400 | 34,790 | 6,075 | 10,810 | 10,810 | 9,792 | 2013–14 |
Total Conventional Border | 59,400 | 59,400 | 34,790 | 6,075 | 10,810 | 10,810 | 9,792 | |
Enforcement | ||||||||
Analysis and Design | ||||||||
Biometrics | 12,690 | 12,070 | 8,900 | 3,650 | 3,650 | 3,650 | 3,140 | 2012–13 |
Total Enforcement | 12,690 | 12,070 | 8,900 | 3,650 | 3,650 | 3,650 | 3,140 |
Notes:
1 Very first Treasury Board Expenditure Authority Decision for total projects cost.
2 Most Recent Tresury Board Expenditure Authority decision for total project cost.
3 All expenditures to date including the current year (year determined by Treasury Board of Canada Secretariat).
4 Planned spending: Updated Main Estimates.
5 Total authorities comprise Main Estimates, Supplementary Estimates and Internal Transfers.
6 Fiscal Year: Final year before project enters ongoing maintenance phase.
Costs for individual projects are attributable to many program activities; only the most significant ones have been identified.