Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Status Report on Projects Operating with Specific Treasury Board Approval


($ thousands)
Project Original Estimated
Total Cost 1
Revised Estimated
Total Cost 2
Actual
Cost Total 3
2010-11
Main
Estimates
Planned
Spending4
Total
Authorities5
Actual Expected date of
close-out6
 Internal Services
 Close-Out
Housing infrastructure, B.C. and Yukon  10,000 10,000  9,623  9,574  9,574  9,582 9,205 2010–11
St. Stephen, N.B.  21,508 21,508 22,811 100 100 100 97 2010–11
Implementation and Development
Non-housing Infrastructure, B.C. and Ontario  70,000  70,000 11,920 23,798 11,132 32,795 10,792 2011–12
Douglas, B.C.  45,000 45,000 47,692 312 312 312 241 2011–12
Andover, N.B. 6,445 6,445 8,094 327 192 327 192 2011–12
Rigaud, Quebec  54,000 57,574 9,742  25,877  6,349  25,877  5,352 2012 –13
Saint-Bernard-de-Lacolle,Quebec (commercial expansion)  10,000  10,000  429 476 443  476 306 2013–14
Harmonized Risk Scoring-Advance Trade Data 5,575 5,575  2,102 1,129 1,129 1,129  406 2011–12
Air Cargo 1,184 1,184 153     690 153 2011–12
eManifest 19,800 19,800 11,597 2,025 3,603 3,603 3,264 2013–14
 Initial Planning and Identification
Beaver Creek, Yukon 6,600 6,600 507 253 253 253 253 2013–14
Aldergrove, B.C. 15,000 12,000 183 86 86 86  29 2013–14
Total Internal Services 265,112 265,686 124,853  63,957 33,173 75,230 30,290  
Risk Assessment
Implementation and Development
eManifest 316,801 316,801 185,549 32,401 57,654 57,654 52,226 2013–14
Harmonized Risk Scoring-Advance Trade Data 33,289 33,289 15,879 6,740 6,740 6,740 4,938 2011–12
Air cargo 5,138 5,138 2,039     2,335 2,039 2011–12
Total Risk Assessment 355,228 355,228  203,467 39,141 64,394 66,729 59,203  
Conventional Border
Implementation and Development
eManifest 59,400 59,400 34,790 6,075 10,810 10,810 9,792 2013–14
Total Conventional Border 59,400 59,400 34,790 6,075 10,810 10,810 9,792  
Enforcement
Analysis and Design
Biometrics  12,690 12,070 8,900 3,650 3,650 3,650 3,140 2012–13
Total Enforcement  12,690 12,070 8,900 3,650 3,650 3,650 3,140  


Notes:

1 Very first Treasury Board Expenditure Authority Decision for total projects cost.
2 Most Recent Tresury Board Expenditure Authority decision for total project cost.
3 All expenditures to date including the current year (year determined by Treasury Board of Canada Secretariat).
4 Planned spending: Updated Main Estimates.
5 Total authorities comprise Main Estimates, Supplementary Estimates and Internal Transfers.
6 Fiscal Year: Final year before project enters ongoing maintenance phase.

Costs for individual projects are attributable to many program activities; only the most significant ones have been identified.