Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Project | Original Estimated Total Cost 1 |
Revised Estimated Total Cost2 |
Actual Cost Total 3 |
2009-2010 | ||||
---|---|---|---|---|---|---|---|---|
Main Estimates |
Planned Spending |
Total Authorities |
Actual | Expected date of close-out 4 |
||||
Staffing Services and Assessment Program Activity | ||||||||
Public Service Staffing Modernization Project (PSSMP) and Other Tools (Note A) | 48,150 | 65,606 | 60,468 | 0 | 6,670 | 8,757 | 8,635 |
March 31, 2011 |
Total | 48,150 | 65,606 | 60,468 | 0 | 6,670 | 8,757 | 8,635 |
|
Note A: In the 2008-2009 Departmental Performance Report, the financial information of this chart was broken down between the “Public Service Resourcing System (PSRS)” and the “longer-term solution” components. In 2009-2010, the development of the longer-term solution has been abandoned. Only the PSRS and other tools remain part of the PSSMP.
1. First Treasury Board Expenditure Authority decision for total project cost
2. Most recent Treasury Board Expenditure Authority decision for total project cost
3. All expenditures to date, including the current year
4. Fiscal year