Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Status Report on Major Crown/Transformational Projects

Description:

Canada-U.S. Bi-National Transportation Partnership planning new Detroit River International Crossing (DRIC), composed of:

  • Transport Canada
  • U.S. Federal Highway Administration (FHWA)
  • Ontario Ministry of Transportation (MTO)
  • Michigan Department of Transportation (MDOT)

The project is a U.S./Canadian, I-75 to Highway 401, end-to-end solution consisting of five components: a new international crossing; the Canadian customs plaza; the U.S. border inspection plaza; the interchange between the U.S. bridge/plaza and Interstate 75; and the highway connector between Canadian bridge/plaza and Highway 401.

It is the Partnership's intention to seek a public-private partnership (P3) for the bridge and plaza portion of project.

The Bridge

The new Detroit River crossing will be a six-lane bridge that will provide three Canada-bound lanes and three U.S.-bound lanes. The new crossing will accommodate future travel demand, both in terms of providing capacity and flexibility to stream traffic on the crossing to improve border process (e.g. designated Nexus/fast lane).

The new crossing will be constructed to link inspection plazas on the Canadian and U.S. sides of the Detroit River, and will be a key component of the new end-to-end transportation system that will link the existing Highway 401 to the U.S. Interstate system. The crossing will consist of both a main bridge that will span the width of the Detroit River and designed to provide navigational clearances that meet U.S. and Canadian requirements, and approaches to the main bridge that will connect to plazas in both Canada and the United States.

Selection of the bridge type will be made during subsequent design phases of this project and will not require piers to be placed in the Detroit River.

Border Services Plaza

In Canada, border inspection plaza alternatives were developed in consideration of the need to provide improved border processing facilities to meet future travel demand and security requirements at the border crossing. The new plaza will be designed to serve the future (2035 and beyond) travel demands at the border crossing. Initial construction of the plaza may not include the fully developed plaza, as the plaza may be developed in stages. The initial construction of the plaza will be such that future expansion will be possible by way of constructing additional inspection or tollbooths.

The plaza was developed in consultation with Canada Border Services Agency and provides sufficient area for primary inspection lane booths and on-site secondary inspection of people and goods. The plaza also allows for dedicated Nexus and fast lanes and provides for a substantial improvement of border crossing processing capabilities.

The plaza will be situated within the Brighton Beach Industrial Park; bounded by the Detroit River, Chappus Street, Ojibway Parkway and Broadway Street. The plaza includes: total plaza area of 202 acres (72.8 hectares); total of 29 inbound inspection lanes; total of 103 secondary inspection parking spaces for commercial vehicles; nine toll collection lanes; and storm water management features to control quality and quantity of runoff rain water.

Ontario Access Road

The new access road will be a controlled access highway connection approximately 11 kilometres long located between the Border Services Plaza and the provincial highway network. The connection is a six-lane urban freeway involving interchanges, grade separations, road closings and the use of service roads. The connection includes a combination of below-grade, at-grade, and above-grade segments and eleven short-tunnelled (or covered) sections. The width of the right-of-way varies and where possible, existing rights-of way will be utilized. Along the corridor, the maximum width of the new right-of-way, not including the existing right-of way, is approximately 300 meters.

Ontario is responsible for the delivery of the Windsor-Essex Parkway, which will connect Highway 401 with the new border inspection plaza and bridge. The province is in the midst of the procurement process and on October 8, 2009, announced a shortlist of three qualified bidders to move to the request-for-proposal stage.

The Rationale for the Project:

Windsor-Detroit is the busiest land border crossing in North America:

  • $130 billion (2006 Canadian dollars) of two-way surface trade.
  • 28% of total Canada-U.S. trade.
  • Consists of four crossings: Windsor-Detroit tunnel, Ambassador Bridge, truck ferry and Canadian Pacific Railway tunnel.
  • Ambassador Bridge alone handles 99% of Windsor-Detroit truck traffic.
  • In recent years, there have been increased traffic delays due to heightened security checks at the U.S.– Canada border. Inefficiencies at the border crossing directly affect costs; thus affecting abilities to compete internationally.
  • Truck Traffic is expected to triple and vehicle traffic to double over the next 30 years.

Project Phase:

On December 3, 2009, the federal environmental assessment for the new bridge, customs plaza and access road to the bridge – the Windsor-Essex Parkway - was approved. The Province of Ontario commenced some advance construction of the Windsor-Essex Parkway in early 2010, while also advancing its procurement process for the remainder of the Parkway project.


Leading and Participating Departments and Agencies
Lead Department Transport Canada
Contracting Authority Deloitte
Participating Departments Canada Border Services Agency, Public Works and Government Services Canada, Department of Fisheries and Oceans, Environment Canada


Prime and Major Subcontractor(s)
Prime Contractor Deloitte
181 Bay Street, Suite 1100, Toronto, ON, M5J 2V1 Canada
Direct 416-643-8382 | Fax 416-601-6690
Major Subcontractor(s)

Investment Grade Traffic & Revenue Forecast:

Wilbur Smith Associates
9500 Arboretum, Suite 360, Austin, TX, U.S.A., 78759

Air Quality Advisor:

Stantec
100 - 401 Wellington Street West, Toronto, ON, M5V 1E7

Cost Consultant:

Davis Langdon
1717 Arch Street, Suite 3720, Philadelphia, PA, U.S.A., 19103

Bridge Technical Advisor:

Delcan
625 Cochrane Drive, Suite 500, Markham, ON, L3R 9R9



Major Milestones
Major Milestone Date
1. Environmental Assessment launched with 15 options considered. February, 2005
2. Options narrowed to 3 potential crossing locations, 3 potential plaza locations and 5 potential access road designs. March, 2006
3. Announcement of the technically preferred Ontario Access Road. May 1, 2008
4. Announcement of the technically and environmentally preferred alternative for the crossing and plaza locations. June 18, 2008
5. U.S. Final Environmental Impact Statement published for final comment. December 5, 2008
6. Final Ontario Environmental Assessment Report submitted to the Ontario Ministry of the Environment / Canadian Environmental Assessment Final Screening Report submitted to the Canadian Environmental Assessment Agency. December 31, 2008
7. U.S. Record of Decision. January 14, 2009
8. Approval of Ontario's Environmental Assessment. August 24, 2009
9. Approval of Federal Environmental Assessment. December 3, 2009

Project Outcomes

The beneficiaries of the Detroit River International Crossing will be both the Canadian and United States economies and all users of the new bridge.

Progress Report and Explanations of Variances


Project Approvals

  • Approval and necessary authorities were provided in December 2006, to continue advancing the development of a new Detroit River crossing for the Windsor-Detroit Corridor.
  • The March 2007 Federal Budget supported the development of a new Detroit River Crossing for the Windsor-Detroit Corridor and provided $10 million over three years for this purpose.
  • The Detroit River International Crossing project has been identified as a Major Crown Project as the total value is beyond the $100 million threshold. The entire project cost for Canada was estimated at $2.01 billion. Preliminary Project Approval to provide authorization to expend resources to fully define the Detroit River International Crossing Project was sought.
  • Approval to continue to advance the development of a new Detroit River Crossing for the Windsor-Detroit Corridor was provided in December 2007.
Property Acquisition

  • In June 2009, expenditure authority approvals were provided for Phase I implementation of the Detroit River Crossing Major Crown Project for the acquisition and implementation of infrastructure projects related to the first of two groups of properties, for the Canadian-half of the new international bridge and its Canadian customs plaza, at a substantive cost of $60.9 million inclusive of GST of $2.9 million.
  • On July 20, 2009, the Government of Canada announced that it purchased 94 acres of land from the City of Windsor for $34 million for the new Canadian inspection plaza and Canada's portion of the six-lane bridge. This purchase represents the largest single block of land needed for the new crossing and plaza. TC, with Public Works and Government Services Canada (PWGSC), is in active negotiations with property owners to acquire the remaining properties required for the bridge and plaza.
  • On October 19, 2009, TC acquired 5 parcels of land (1.2 acres) from James Sylvestre Developments Ltd. TC and PWGSC acquired on March 16, 2010 an additional 5 parcels of land (1.1 acres) from two individual property owners. TC is in active negotiations with the four remaining individual property owners to acquire the remaining properties for the Canadian customs plaza.
  • Discussions and studies that were to be completed for TC to have substantive costs for the acquisition of four industrial properties and for the necessary utility relocation submissions have taken longer than originally anticipated. Although these studies are currently underway and negotiations with the utility and industrial owners are progressing well, these delays meant that TC will be returning to Treasury Board in Spring 2011.
Project Progress

  • In August 2009, the Ontario Minister of the Environment approved the environmental assessment for the Windsor-Essex Parkway. The Canadian environmental assessment (EA) for DRIC was approved on December 3, 2009 by the Responsible Authorities (Transport Canada (TC), the Department of Fisheries and Oceans and the Windsor Port Authority).
  • While important milestones were achieved in 2009 for the DRIC project, including the approval of the requisite environmental assessments in both countries, future progress on the new crossing is being threatened by multiple legal and trade challenges as well as the uncertainty of project approval in Michigan.
  • On September 30, 2009, the Conference Committee of the Michigan Legislature (House and Senate) agreed that the Michigan legislature fully adopt or reject authorizing legislation by June 1, 2010, to construct a new crossing jointly and in agreement with Canada; to create an authorized tolling authority; and to create a public-private partnership.
  • On April 29, 2010, the Michigan Department of Transportation presented a report to the Michigan Legislature responding to the legislative requirements. As well, Michigan Governor Jennifer Granholm read into the Legislature record a letter from Minister Baird stating that the Government of Canada is prepared to offer to increase its financial participation up to a maximum of US $550 million, for project components in Michigan that would not be funded by the public-private partnership or the United States Government.
  • The Transportation Committee of the Michigan Legislature passed the Bill on April 29, 2010. The Bill was passed by the full House on May 26, 2010 and has been forwarded to the Senate for deliberations and decisions.

Industrial Benefits

The investment in new border infrastructure will result in a number of positive economic impacts. Recently conducted studies concluded that the direct and indirect (e.g. materials, equipment, services, etc.) impacts of the entire border infrastructure project will lead to the creation of approximately 23,000 jobs; including approximately 13,000 direct, and 10,000 indirect employment opportunities. This is particularly noteworthy in that Statistics Canada has reported that the Windsor-Essex region has maintained one of the highest unemployment rates in Canada. Ancillary benefits of these jobs are expected to result in increases in consumer spending, as personal income and company profits improve in the region.

Additionally, the project will provide significant opportunities for local businesses to participate in construction related aspects of the project's implementation.

Transportation

The vast majority, 62%, of Canadian and U.S. bi-lateral trade crosses our shared border by land. Each day, almost 36,000 trucks cross the Canada-U.S. border, close to one-third (12,000 trucks) of those at Windsor-Detroit. This project will improve not only the efficiency of the border crossing in the region, but will also provide direct highway connections, thereby reducing costs associated with shipping, and greenhouse gas emissions and other pollutants resulting from idling vehicles.

Over the next 30 years, trade between Canada and the U.S. is projected to increase. Under high-growth scenarios, cross-border traffic demand could exceed the capacity of the present border crossings in the Detroit River area as early as 2015.

Economic

Given the significant interdependency of the Canadian and American economies, there is nothing more important to exporters and importers on both sides of the border than being able to ensure that traffic at the border flows efficiently and that the international supply chain remains strong.

Businesses from coast-to-coast in Canada and the United States depend on a reliable and secure transportation network. Manufacturing production depends heavily on the fast and predictable trucking of components, parts and finished products across the border, particularly between Windsor-Detroit.

It is estimated that the direct and indirect impact of the entire border infrastructure project on the province's GDP will be $1.6 billion. Additionally, utilizing Ontario's two-thirds attribution ratio, it is expected that approximately 15,000 total jobs will occur in the Windsor-Essex Region, while contributing an estimated $587 million to the GDP of the Windsor-Essex region.

Security

The Bi-national Partnership is working with border inspection agencies in both countries to ensure that the proposed border processing facilities meet future travel demand and their security requirements at the border crossing. The plazas will be designed to serve future (2035 and beyond) travel demands. These new plazas are being developed in consultation with the Canada Border Services Agency and the U.S. Department of Homeland Security, Customs and Border Protection Branch, to provide sufficient areas for primary inspection-lane booths and on-site secondary inspection of people and goods. The plaza designs will allow for dedicated Nexus and fast lanes and will provide for a substantial improvement of border processing capabilities including areas for permanent gamma ray inspection equipment.

With almost $2 billion (CDN) daily in cross-border trade with the United States, keeping the trade system open and flowing efficiently is critical to ensuring both countries economic prosperity. It is equally critical to protect the border against potential threats to our health, security and economy. Redundant infrastructure will help keep the border open in case of incidents at other crossings.