Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Status Report on Projects operating with specific Treasury Board Approval


($ millions)
Project Original Estimated
Total Cost [1]
Revised Estimated
Total Cost [2]
Actual
Cost Total [3]
2009-10
Main
Estimates
Planned
Spending
Total
Authorities
Actual Expected date of
close-out [4]
Detroit River Crossing – Total Project Cost $2.01
Billion
$2.01
Billion
$38.92 $64.5 $64.5 $64.5 $32.4 2017-2018
Fort Nelson Airport Environmental Remediation [5] $20.4 $35.7 $20.6 Note [6] Note [7] $5.7 $4.6 2014-2015
Canadian Air Cargo Security Program [8] $600.0 $153.6 $31.0 0 $10.3 $10.5 $10.4 2015-2016

*Note that numbers have been rounded off to save space.

[1] Very first Treasury Board Expenditure Authority decision for total project cost.
[2] Most recent Treasury Board Expenditure Authority decision for total project cost.
[3] All expenditures to date including the current year.
[4] Fiscal year.
[5] Numbers exclude GST and Employee Benefits Plan (EBP).
[6] 100% funded by FCSAP in 2009-2010.
[7] 100% funded by FCSAP in 2009-2010.
[8] EBP, accommodation and costs for the Canada Border Services Agency (CBSA) are included in the "Original Estimated Total Cost" and the "Revised Estimated Total Cost" columns only. These costs are excluded from the amounts indicated in the other columns.