Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

3.3.3) Status Report on Projects operating with specific Treasury Board Approval

($ in millions)
Program Activity/Project Original Estimated Total Cost [1] Revised Estimated Total Cost [2] Actual Cost Total [3] 2009-2010
Main Estimates Planned Spending Total Authorities Actual Expected date of close-out [4]
Space Base Earth Observation
RADARSAT-2 MCP (EPA) 242.1 433.6 417.8 0.7 0.7 0.1 0.1 2010-2011
CHINOOK MCP (PPA) [5] 105.5 105.5 6.2 - - - - TBD
RADARSAT CONSTELLATION MCP (PPA) 600.0 600.1 62.9 40.3 40.3 39.4 39.4 2016-2017
Science and Exploration
ALPHA PARTICLE X-RAY SPECTROMETER (EPA) (APXS) 8.6 9.6 9.3 0.1 0.1 0.3 0.3 2011-2012
JAMES WEBB SPACE TELESCOPE MCP (EPA) (JWST) 49.3 144.9 126.1 23.6 23.6 27.7 27.7 2013-2014
MARS PHOENIX (EPA) 21.5 28.6 28.1 - - 0.3 0.3 2009-2010
NEAR EARTH OBJECT SURVEILLANCE SATELLITE (EPA) (NEOSSAT) 5.4 8.4 5.2 1.6 1.6 2.1 2.1 2010-2011
ULTRA-VIOLET IMAGING TELESCOPE (EPA) (UVIT) 5.3 5.9 5.7 0.9 0.9 1.0 1.0 2010-2011
Satellite Communication
MARITIME MONITORING AND MESSAGING MICRO-SATELLITE (EPA) (M3MSAT) 5.4 7.0 1.8 1.7 1.7 1.3 1.3 2011-2012

[1] Very first Treasury Board Expenditure Authority decision for total project cost.
[2] Most recent Treasury Board Expenditure Authority decision for total project cost.
[3] All expenditures to date including the current year.